Procore Connection Map
The Rebuild — Procore Tips
How Procore’s own tools feed each other, laid out left to right in project order. Click any tool to see what it sends and receives. Pick a workflow to trace it step by step. Every link carries its source.
What this is
Procore is a platform, which means the value is in the handoffs: an RFI that becomes a change event, a change event that becomes a commitment change order, a commitment that becomes an invoice that becomes a payment that lands in accounting. This map draws only those purpose-built handoffs — create, convert, send, sync — and leaves out the generic “Related Items” links that nearly every tool has. If a line is on the map, a Procore support page describes it, or the line says it doesn’t.
Create, convert, send, pull, sync. Generic cross-links are left off so the picture shows how the platform is designed to move data.
Solid lines link to the current Procore support article or developer reference. Dashed lines are documented only on Procore’s previous support site, with no current page yet, and link there. Handoffs the public docs don’t describe aren’t drawn.
Owner-side tools are left out. Beta and limited-availability tools carry a badge and a source, dated, so you can tell what has changed since.
The map
List view: pick a tool and see what it sends and receives
This map started with Nick Trejo, my teammate on Procore’s enterprise specialty contractor team, who built the first version and shared it with me. If you want to go deeper (mapping your own processes and digitizing them), talk with your Procore account team and Louis Tigh at Strategic Adoption. Together they can help you trim your tech stack, raise adoption, and make decisions from data your team enters once.
The workflows
- Bid → Estimate → Budget → ERP — Awarded pricing becomes the project budget and syncs to accounting: Bid Management → Estimating → Budget → ERP Integrations
- Bid → Commitment → Invoice → Pay — Awarded sub is contracted, billed against its SSOV, paid, and the payment syncs: Bid Management → Commitments → Invoicing → Procore Pay → ERP Integrations
- RFI → Change Event → CO → Budget — A design question becomes priced scope and committed cost: RFIs → Change Events → Commitment Change Orders → Commitments → Budget
- RFI → Prime CO → Owner billing — Owner-side change is approved and billed, with the invoice exported: RFIs → Change Events → Prime Change Orders → Prime Contracts → Invoicing → ERP Integrations
- Clash → RFI → Change — A model clash is formalized and priced: Models → Coordination Issues → RFIs → Change Events
- Inspection → Observation → Change — A failed item becomes a tracked observation and, if needed, a budget change: Inspections → Observations → Change Events → Budget
- Specs → Submittals — Spec book generates the submittal log, linked to drawings: Specifications → Submittals → Drawings
- Timecards → Daily Log → Budget (labor productivity) — Timesheets and the Daily Log share the same timecard entries. Their hours and installed quantities land in the Budget's Labor Productivity Cost view, next to budgeted hours and quantities. That view needs Procore's Resource Tracking tools and an admin to set it up; other budget views can add a 'Timesheet Hours' column: Timesheets (Project) → Daily Log → Budget
- Estimate → Budget → Timesheets → Field Production Report — Estimated hours become budgeted pickers; installed units and hours report against them: Estimating → Budget → Timesheets (Project) → Field Productivity
- Incident → Corrective Action → Observation — An incident's corrective or preventive action is assigned and tracked as an observation; an action plan can then link that observation as a record: Incidents → Observations
- Equipment → Timesheet → Budget — Equipment hours logged on timesheets are visible in the budget: Equipment → Timesheets (Project) → Budget
- Resource Planning → Timesheets → Payroll — Resource Planning syncs people into the Directory; anyone in the Directory marked as an employee of your company can be added to project timesheets, which roll up for weekly approval at company level. For payroll, an integration reads the timecard data through the REST API ('List all Timesheets' per project, or 'List Timecard Data' company-wide); Sage 300 CRE users also have a documented file export: Resource Planning → Directory → Timesheets (Project) → Timesheets (Company) → Webhooks / REST API
- Meeting → Change Event — A cost-impacting discussion becomes a change event, linked back to the meeting it came from: Meetings → Change Events
- Change Event → RFQ → Commitment Change Order — Subs price the change event's lines through RFQs. When a reviewed quote is set to 'Pending Final Approval', the commitment change order you create from those lines fills in with the quoted amounts, and the approved CCO revises the commitment: Change Events → RFQs → Commitment Change Orders → Commitments
- Bid Board → Portfolio → Estimating → Budget — The estimate does not jump to the Budget on its own. Adding the won project to Portfolio creates the Procore project and carries the estimate into its Estimating tool; someone then sets the primary estimate and runs Send to Budget, which copies its cost codes and amounts in as budget line items (Project Financials required): Bid Board → Portfolio → Estimating → Budget
- PO → Receipt → Supplier Invoice — Materials you receive against your purchase order are posted as a receipt, and Procore drafts the supplier's invoice on that PO for you to review and pay. This is accounts payable; your own billing to the GC runs through prime contract invoicing: Commitments → Materials → Invoicing
Every tool, every connection
Jump to a lane: Precon & Company · Design & Documents · Project Communication · Field & Quality · Change Management · Contracts & Cost · Resource Management · Company & Platform · Payment & Accounting
Precon & Company
Directory
Company and project directory of companies, people, permissions and vendor insurance records.
Sends to / links with · 11
- Bid Management — Invite bidding companies from the Directory (or add new ones from the bid tool). source
- Daily Log — Resources for Scheduled Work must exist in the Project Directory. source
- Equipment — Link rented/subcontracted equipment to a vendor. source
- Resource Planning — Two-way sync of first/last name, employee ID, mobile, email, status; job title RP→Directory only. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Insurance (Directory) — Insurance documents are recorded on the company profile in the Directory (system of record). source
- ERP Integrations — Vendors sync (Vista: both; Workday: Workday→Procore). source
- Crews — Adding a worker in Crews also creates the worker as a contact in the Project and Company Directory; edits sync either way. source
- Conversations — Group conversations import and stay in sync with the project Directory; distribution groups are selectable as recipients. source
- Planroom — Bidders must be in the Company Directory before they can be invited; adding a company to a bid package grants its bidders Planroom access. source
- Timesheets (Project) — Timesheets draw people from the Directory: only people in the Directory who are marked as employees of your company can be added to a timesheet. source
Receives from · 0
- Nothing purpose-built.
Construction Network GAUS/CA per the cited page
Procore's network of companies (US and Canada) used to find and invite bidders.
Sends to / links with · 2
- Bid Management — Invite bidders from the Procore Construction Network (US/CA). source
- Bid Board — Invitations received through the Procore Construction Network land in the Bid Board. source
Receives from · 0
- Nothing purpose-built.
Bid Management GA"enhanced experience"
Bid packages, bidder invitations, leveling and award to a commitment.
Sends to / links with · 5
- Estimating — Link leveled bid values to the estimate ("Show Bid in Estimating" → "Set as Estimate Value"). source
- Commitments — Award a bid and convert it to a subcontract or purchase order. source
- Estimating — Create bid packages directly from an estimate; awarded bids can update the estimate. source
- Planroom — Bid packages created in a project's Bidding tool are published to invited bidders in the Planroom, where they download bid documents. source
- Bid Board — Bid invitations sent from other companies' Bidding tools appear in the Bid Board; intent-to-bid responses notify the sender. source
Receives from · 5
- Directory — Invite bidding companies from the Directory (or add new ones from the bid tool). source
- Construction Network — Invite bidders from the Procore Construction Network (US/CA). source
- Drawings — Drawings go out with bid packages. source
- Specifications — Spec sections go out with bid packages. source
- Planroom — Bidders submit bids, intent to bid and pre-bid questions in the Planroom; the solicitor reviews them in the Bidding tool. source
Estimating
Procore Estimating: estimates, proposals, bid packages from estimates, send to Budget and Change Events.
Sends to / links with · 6
- Budget — Send to Budget copies the primary estimate's line items into the project Budget; its cost codes and amounts become the budget lines (Project Financials required). source
- Change Events — Send an estimate change order to the Change Events tool (costs only or full estimate with adjustments); budget codes update. source
- Bid Management — Create bid packages directly from an estimate; awarded bids can update the estimate. source
- Prime Contracts — Create a prime contract from an estimate. source
- Commitments — Create a purchase order from an estimate. source
- Cost Catalog — Create new catalog items directly from a takeoff or estimate. source
Receives from · 4
- Bid Management — Link leveled bid values to the estimate ("Show Bid in Estimating" → "Set as Estimate Value"). source
- Takeoff — Takeoff quantities flow directly into the estimate. source
- Cost Catalog — Catalog parts and assemblies are selected into estimate groups as line items, and pulled into takeoff layers via Browse Catalog. source
- Portfolio — Adding a won Bid Board project to Portfolio creates the Procore project, and you keep working on the same estimate in that project's Estimating tool. source
Takeoff GAfeature of Estimating
Quantity takeoff inside Procore Estimating from uploaded plans or 3D models; "Takeoff data flows directly to" the estimate.
Insurance (Directory) GAnot a standalone tool; lives in Directory
Vendor insurance documents held on the Directory company profile; status surfaces on the commitment Compliance tab and gates Procore Pay.
Sends to / links with · 1
- Commitments — Commitment Compliance tab shows Directory insurance entries and an automatic Compliant / Not Compliant status. source
Portfolio GApage titled "Procore Home (Legacy Company Portfolio)"
Company-level list/map of projects; project creation, templates, Send to ERP.
Sends to / links with · 3
- Resource Planning — Push projects from the Portfolio tool to Resource Planning (recommended when an ERP is integrated). source
- ERP Integrations — "Send to ERP" during project creation; projects/jobs sync both ways (Vista, Workday). source
- Estimating — Adding a won Bid Board project to Portfolio creates the Procore project, and you keep working on the same estimate in that project's Estimating tool. source
Programs GAmodernized layout 2025-01-08
Groups projects into named programs for sorting.
Cost Catalog
Company-level store of material parts and assemblies with values, used during takeoff and estimating. Procore supplies predefined materials; companies add and customize their own.
Sends to / links with · 2
- Estimating — Catalog parts and assemblies are selected into estimate groups as line items, and pulled into takeoff layers via Browse Catalog. source
- Bid Board — Catalog items are used in Bid Board's Estimating and Takeoff tabs. source
Receives from · 2
- Estimating — Create new catalog items directly from a takeoff or estimate. source
- ERP Integrations — ERP cost codes can be added to the Cost Catalog for ERP-integrated companies and applied across Estimating and Bid Board; they carry to the budget when an estimate is sent. source
Planroom
The bidder-facing side of a bid solicitor's Bidding tool: invited bidders view bid packages and submit bids here.
Sends to / links with · 2
- Bid Management — Bidders submit bids, intent to bid and pre-bid questions in the Planroom; the solicitor reviews them in the Bidding tool. source
- Bid Board — Accounts with a Bid Board license open invitations in the sender's Planroom but view and submit from their own Bid Board. source
Receives from · 2
- Bid Management — Bid packages created in a project's Bidding tool are published to invited bidders in the Planroom, where they download bid documents. source
- Directory — Bidders must be in the Company Directory before they can be invited; adding a company to a bid package grants its bidders Planroom access. source
Bid Board GAFree Procore accounts that use Bid Board are a limited release in the US and Canada. source
Where a company manages every bid it has been invited to: intent to bid, takeoff and estimating, and moving awarded work into the Portfolio as a live project.
Sends to / links with · 4
- Bid Management — Bid invitations sent from other companies' Bidding tools appear in the Bid Board; intent-to-bid responses notify the sender. source
- Portfolio — Add a Bid Board project to the Portfolio tool, creating a full Procore project (optionally from a template). source
- Budget — A Bid Board estimate reaches the Budget only after the project is added to Portfolio; Send to Budget is then run from the project's Estimating tool. source
- Commitments — Create a purchase order in Commitments from a Bid Board estimate (after the estimate is sent to budget). source
Receives from · 3
- Cost Catalog — Catalog items are used in Bid Board's Estimating and Takeoff tabs. source
- Planroom — Accounts with a Bid Board license open invitations in the sender's Planroom but view and submit from their own Bid Board. source
- Construction Network — Invitations received through the Procore Construction Network land in the Bid Board. source
Design & Documents
Drawings
Drawing sets and markups; the most-linked tool.
Sends to / links with · 16
- Bid Management — Drawings go out with bid packages. source
- RFIs — Create or link RFIs on a drawing markup. source
- Submittals — Link submittals on a drawing markup. source
- Documents — Link documents on a drawing markup. source
- Punch List — Add punch list items to a drawing / link on markup. source
- Observations — Link observations on a drawing markup. source
- Inspections — Link inspections on a drawing markup. source
- Coordination Issues — Link coordination issues on a drawing markup. source
- Correspondence — Link correspondence items on a drawing markup. source
- Takeoff — Perform takeoff on uploaded plans (Standard permission on Drawings needed for layer actions). source
- Models — Map 2D PDF sheets to the 3D model (multisheet mapping). source
- Action Plans — Attach drawings as action plan attachments. source
- Locations — Generate the location hierarchy from drawings. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Conversations — Link a drawing or attach drawing files to a message. source
- Connection Manager — Published drawings and drawing areas sync from an upstream project to a downstream project and stay in sync; markups and custom fields are excluded. source
Receives from · 3
- Photos — Photos can be pinned to drawing locations. source
- Document Management — Import Document Management files into the Drawings tool with metadata. source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
Specifications GASubmittal Builder: US/CA/AU, English
Spec book by section; Submittal Builder generates submittals.
Sends to / links with · 3
- Bid Management — Spec sections go out with bid packages. source
- Submittals — Submittal Builder generates submittals from vector-PDF spec sections. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
Receives from · 1
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
Models
3D model viewing; 2D sheet mapping; issues from viewer.
Sends to / links with · 4
- Coordination Issues — Create a coordination issue directly from the model viewer's Issues side panel. source
- Takeoff — Perform 3D model takeoffs (Read Only on Models required). source
- Drawings — Map 2D PDF sheets to the 3D model (multisheet mapping). source
- Observations — Create an observation from a model (iOS). source
Coordination Issues
Clash/design issues; elevate to RFI.
Sends to / links with · 4
- Drawings — Link coordination issues on a drawing markup. source
- RFIs — Elevate a coordination issue to a new or existing RFI (status → Elevated/Released). source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Conversations — Link a coordination issue in a message. legacy source
Receives from · 2
- Models — Create a coordination issue directly from the model viewer's Issues side panel. source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
Documents
Project file repository; models can be published from it.
Sends to / links with · 7
- Drawings — Link documents on a drawing markup. source
- Models — Publish models to the Models tool from the Documents tool. source
- Action Plans — Attach files from Documents (and Drawings, Forms) as action plan records. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Transmittals — Add a document as a transmittal line item. source
- Conversations — Link a document or attach files from Documents to a message. source
- Assets — Pull model objects from a BIM file in Documents or Document Management, filter by property, and map them to asset types for bulk import; assets can be viewed in the 3D model. source
Receives from · 1
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
Document Management GANot available to US accounts (GA in UK/IE/AU/NZ; "not yet for U.S. accounts") source
Attribute-driven document control with approval workflows; import into Drawings; SharePoint link.
Sends to / links with · 2
- Drawings — Import Document Management files into the Drawings tool with metadata. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
Receives from · 2
- Workflows — Approval workflow on Document Management documents (select regions). source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
Schedule
Project schedule (imported MS Project/P6 etc.); tasks feed Daily Log and Submittal schedule fields.
Sends to / links with · 3
- Submittals — A submittal's Schedule Task field ties it to a schedule task for required-on-site/lead-time calculations. source
- Daily Log — Scheduled Work entries carry resource and task name from schedule tasks for that day. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
Receives from · 0
- Nothing purpose-built.
Photos
Project photo albums.
Sends to / links with · 5
- Drawings — Photos can be pinned to drawing locations. source
- Daily Log — Photos attach to the Daily Log (Photos section). source
- Action Plans — Add photos from the Photos tool as action plan records. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Project Map — Photos with GPS data display as pins on the Project Map; pins can be placed from the map and written back. source
Project Communication
RFIs GADraft RFI with AI: Beta
Requests for information; hub for creating change events, PCOs, correspondence, instructions.
Sends to / links with · 9
- Drawings — Create or link RFIs on a drawing markup. source
- Change Events — Create a change event from an RFI. source
- Correspondence — Create a correspondence item from an RFI. source
- Prime Change Orders — Create a potential change order from an RFI. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Transmittals — Add an RFI as a transmittal item. source
- Project Map — RFIs with location data display as pins on the Project Map (mobile). source
- Conversations — Send a message about an RFI; the thread appears on the item and in Conversations. source
- Connection Manager — Closed, non-private RFIs copy read-only to the downstream project's External RFIs tab, where they can be linked to internal RFIs. source
Receives from · 4
- Coordination Issues — Elevate a coordination issue to a new or existing RFI (status → Elevated/Released). source
- Correspondence — Create & Link an RFI from a correspondence item. source
- Locations — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
Submittals
Submittal log, packages, workflows; Schedule Task field.
Sends to / links with · 6
- Drawings — Link submittals on a drawing markup. source
- Action Plans — Create new or link submittals as records. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Transmittals — Add a submittal or submittal package as a transmittal item. source
- Conversations — Send a message about a submittal; the thread appears on the item and in Conversations. source
- Connection Manager — Distributed submittals copy read-only to the downstream project's External Items tab (open beta). source
Receives from · 5
- Specifications — Submittal Builder generates submittals from vector-PDF spec sections. source
- Schedule — A submittal's Schedule Task field ties it to a schedule task for required-on-site/lead-time calculations. source
- Locations — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Assets — Link submittals, RFIs, punch items, incidents, schedule activities and inspection items to an asset from its Related Items tab. source
Correspondence
Configurable correspondence types; create & link RFIs/change events.
Sends to / links with · 5
- Drawings — Link correspondence items on a drawing markup. source
- Action Plans — Create new or link correspondence as records. source
- Change Events — Create & Link a change event from a correspondence item (permanent link). source
- RFIs — Create & Link an RFI from a correspondence item. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
Receives from · 4
- RFIs — Create a correspondence item from an RFI. source
- Workflows — Approval workflow on Correspondence/Custom Tool types. source
- Locations — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
Daily Log
Daily field record with ~20 sections incl. Timecards, Equipment, Scheduled Work, Productivity.
Sends to / links with · 5
- Timesheets (Project) — Timesheet entries auto-populate the Daily Log Timecards section, and Daily Log timecards auto-populate project Timesheets. source
- Timesheets (Company) — Daily Log Timecards carry over to the company Timecard and Company Timesheets tools. source
- Equipment — Daily Log equipment entries pick from the project Equipment tool or company register; equipment timesheets sync with Daily Log entries when fieldsets match. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Budget — Hours and installed quantities on Daily Log timecard entries show in the Budget's Labor Productivity Cost view (Resource Tracking customers; a 'Timesheet Hours' column can be added to other budget views). source
Receives from · 7
- Photos — Photos attach to the Daily Log (Photos section). source
- Schedule — Scheduled Work entries carry resource and task name from schedule tasks for that day. source
- Directory — Resources for Scheduled Work must exist in the Project Directory. source
- Commitments — Unit/Quantity-based subcontracts and POs appear in the Daily Log Productivity section. source
- Locations — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Forms — Attach completed forms (checklists, inspections, permits, sign-offs) from the Forms tool to a Daily Log entry in the mobile app. source
Meetings
Agendas/minutes; create tasks and change events from items.
Sends to / links with · 5
- Action Plans — Create new or link meetings as records. source
- Tasks — Create a task from a meeting agenda item; it also populates the Tasks tool. source
- Change Events — Create a change event from a meeting; meeting details carry over and the meeting is linked in the change event's Origin field. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Conversations — Link a meeting in a message. legacy source
Receives from · 0
- Nothing purpose-built.
Tasks
Project task list; receives tasks created in Meetings.
Sends to / links with · 2
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Conversations — Link a task in a message. legacy source
Emails
Project email log; create change event from an email.
Sends to / links with · 2
- Change Events — Create a change event from an email; the email becomes the Origin Item. source
- Transmittals — Add an email from the Emails tool as a transmittal item. source
Receives from · 0
- Nothing purpose-built.
Transmittals
A documented record of project information sent to others. Items from other tools are added as line items and the transmittal is emailed to recipients for an audit trail.
Sends to / links with · 1
- Conversations — Link a transmittal as a project item inside a Conversations message. legacy source
Receives from · 7
- Documents — Add a document as a transmittal line item. source
- RFIs — Add an RFI as a transmittal item. source
- Submittals — Add a submittal or submittal package as a transmittal item. source
- Prime Contracts — Add a prime contract line item or potential change order as a transmittal item. source
- Punch List — Add a punch list item as a transmittal item. source
- Emails — Add an email from the Emails tool as a transmittal item. source
- Commitments — Add a subcontract or purchase order as a transmittal item. source
Field & Quality
Inspections
Checklist inspections; create observations from items.
Sends to / links with · 6
- Drawings — Link inspections on a drawing markup. source
- Observations — Create an observation from a failed/deficient inspection item; Origin links back. source
- Action Plans — Create new or link existing inspections as action plan records. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Project Map — Inspections with location data display as pins on the Project Map; pins can be placed from the map and written back. source
- Assets — Selecting an asset on an inspection links the inspection to that asset as a related item; bulk-creating inspections by asset is in open beta. source
Observations
Quality/safety/commissioning observations; origin for change events.
Sends to / links with · 6
- Drawings — Link observations on a drawing markup. source
- Change Events — Create a change event from an observation. source
- Action Plans — Create new or link observations as references and records. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Project Map — Observations with location data display as pins on the Project Map; pins can be placed from the map and written back. source
- Conversations — Send a message about an observation; the thread appears on the item and in Conversations. source
Receives from · 6
- Inspections — Create an observation from a failed/deficient inspection item; Origin links back. source
- Models — Create an observation from a model (iOS). source
- Incidents — From an incident action, optionally Create Observation in the Observations tool. source
- Locations — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Assets — Create an observation for one or many assets from the Assets tool; the asset field is pre-filled and the observation is linked back. source
Punch List
Punch items; pin to drawings.
Sends to / links with · 5
- Drawings — Add punch list items to a drawing / link on markup. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Transmittals — Add a punch list item as a transmittal item. source
- Project Map — Punch items with location data display as pins on the Project Map; pins can be placed from the map and written back. source
- Conversations — Send a message about a punch item; the thread appears on the item and in Conversations (not yet on iOS). source
Receives from · 2
- Locations — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
Incidents
Safety incident records; actions can create observations; Equipment field.
Sends to / links with · 4
- Observations — From an incident action, optionally Create Observation in the Observations tool. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Project Map — Incidents with location data display as pins on the Project Map; pins can be placed or moved from the map and written back to the item. source
- Conversations — Link an incident in a message. legacy source
Action Plans
Planned sequences of items with references and required records from six tools.
Sends to / links with · 8
- Inspections — Create new or link existing inspections as action plan records. source
- Observations — Create new or link observations as references and records. source
- Submittals — Create new or link submittals as records. source
- Forms — Create new or link forms as records. source
- Correspondence — Create new or link correspondence as records. source
- Meetings — Create new or link meetings as records. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Assets — Create one action plan per selected asset from a template, each linked to its asset (beta). source
Receives from · 5
- Photos — Add photos from the Photos tool as action plan records. source
- Documents — Attach files from Documents (and Drawings, Forms) as action plan records. source
- Drawings — Attach drawings as action plan attachments. source
- Locations — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
Forms
Fillable PDFs from company Admin templates.
Sends to / links with · 4
- Action Plans — Create new or link forms as records. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Daily Log — Attach completed forms (checklists, inspections, permits, sign-offs) from the Forms tool to a Daily Log entry in the mobile app. source
- Conversations — Link a form or attach form files to a message. source
Receives from · 0
- Nothing purpose-built.
Locations
Multi-tiered location hierarchy managed in project Admin; used by 16 tools.
Sends to / links with · 15
- Action Plans — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Commitments — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Correspondence — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Daily Log — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Incidents — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Inspections — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Observations — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Photos — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Prime Contracts — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Punch List — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- RFIs — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Submittals — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Timesheets (Project) — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Materials — Project storage locations are used as storage, to and from locations on receipts, transfers and issues. source
- Project Map — Draw point, path or polygon geometry for a location on the map; geometry stays synchronized with the Locations tool. source
T&M Tickets GArate tables: beta
Time-and-materials tickets; create change event with all line items.
Sends to / links with · 1
- Change Events — Create a change event from a T&M ticket; all line items transfer and the ticket links in the description. source
Receives from · 2
- Equipment — Use equipment on T&M tickets. source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
Equipment
Project equipment register fed by company Equipment; time in Timesheets/Daily Log; inspections; incidents.
Sends to / links with · 6
- Timesheets (Project) — Track equipment time in Timesheets (equipment timesheets need not be linked to a person). source
- Daily Log — Daily Log equipment entries pick from the project Equipment tool or company register; equipment timesheets sync with Daily Log entries when fieldsets match. source
- Budget — "See time entered for equipment in your budget." source
- Inspections — Create inspections for equipment. source
- Incidents — Incident Equipment field pulls from the Equipment tool. source
- T&M Tickets — Use equipment on T&M tickets. source
Receives from · 2
- Directory — Link rented/subcontracted equipment to a vendor. source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
Project Map BetaTwo things share the name. Maps for Photos (the photo map) has been GA since 2025-01-08. The multi-tool Project Map is still listed as part of the Procore Home open beta on support pages updated 2026-09-16, with Assets added 2026-09-15. source
Procore Maps: one interactive map showing items from several tools as status-colored pins, with location drawing that stays synchronized with the Locations tool. Web only.
Sends to / links with · 7
- Incidents — Incidents with location data display as pins on the Project Map; pins can be placed or moved from the map and written back to the item. source
- Inspections — Inspections with location data display as pins on the Project Map; pins can be placed from the map and written back. source
- Observations — Observations with location data display as pins on the Project Map; pins can be placed from the map and written back. source
- Photos — Photos with GPS data display as pins on the Project Map; pins can be placed from the map and written back. source
- Punch List — Punch items with location data display as pins on the Project Map; pins can be placed from the map and written back. source
- Locations — Draw point, path or polygon geometry for a location on the map; geometry stays synchronized with the Locations tool. source
- Assets — Assets with location data display as pins on the Project Map; pins can be placed from the map and written back. source
Assets GAGA 2026-08-05 (North America, EMEA, APAC). Import from a 3D model is GA in the UK and Ireland and beta in North America; the admin setup guide is still labeled beta. source
The digital thread of a building's fixed assets — HVAC, fire protection, doors, switchgear — from installation through handover. A company-level Asset Register sets the type hierarchy; the project-level tool tracks installed assets, links related records, and exports the full history at turnover.
Sends to / links with · 5
- Observations — Create an observation for one or many assets from the Assets tool; the asset field is pre-filled and the observation is linked back. source
- 360 Reporting — Asset data is available in 360 Reporting at company and project level. source
- Analytics 2.0 — Asset data is available in Procore Analytics. source
- Project Map — Assets with location data display as pins on the Project Map; pins can be placed from the map and written back. source
- Submittals — Link submittals, RFIs, punch items, incidents, schedule activities and inspection items to an asset from its Related Items tab. source
Receives from · 3
- Inspections — Selecting an asset on an inspection links the inspection to that asset as a related item; bulk-creating inspections by asset is in open beta. source
- Action Plans — Create one action plan per selected asset from a template, each linked to its asset (beta). source
- Documents — Pull model objects from a BIM file in Documents or Document Management, filter by property, and map them to asset types for bulk import; assets can be viewed in the 3D model. source
Change Management
Change Events
Hub of change management; creates RFQs, CCOs, PCOs, commitments, budget changes.
Sends to / links with · 8
- RFQs — Create RFQs from change event lines and send to collaborators; quotes return to the lines. source
- Commitment Change Orders — Create (or bulk-create) commitment change orders from change event lines; lines become CCO SOV. source
- Prime Change Orders — Create a Prime PCO / Prime CO from change event lines; lines become SOV. source
- Commitments — Create a subcontract or PO from change event lines, or add lines to an unapproved commitment's SOV. source
- Budget — Create budget changes (adjustment + lines, amount or unit/qty) from change event lines; production quantities carry to the budget. source
- Field Productivity — Approved change-order hours and quantities update the Field Production Report. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Conversations — Send a message about a change event; the thread appears on the item and in Conversations. source
Receives from · 10
- RFIs — Create a change event from an RFI. source
- Observations — Create a change event from an observation. source
- Estimating — Send an estimate change order to the Change Events tool (costs only or full estimate with adjustments); budget codes update. source
- T&M Tickets — Create a change event from a T&M ticket; all line items transfer and the ticket links in the description. source
- Meetings — Create a change event from a meeting; meeting details carry over and the meeting is linked in the change event's Origin field. source
- Correspondence — Create & Link a change event from a correspondence item (permanent link). source
- Emails — Create a change event from an email; the email becomes the Origin Item. source
- Budget — Creating a budget change automatically creates a linked change event. source
- Commitments — Field-initiated change orders submitted by collaborators can auto-create change events (Beta). source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
RFQs GAfeature of Change Events
Requests for quote sent from change event lines.
Sends to / links with · 2
- Change Events — Create RFQs from change event lines and send to collaborators; quotes return to the lines. source
- Commitment Change Orders — Once a sub's RFQ quote is reviewed and set to 'Pending Final Approval', a commitment change order created from those change event lines fills its schedule of values with the quoted amounts. source
Receives from · 0
- Nothing purpose-built.
Prime Change Orders
Potential and approved owner-contract change orders.
Sends to / links with · 2
- Prime Contracts — Approved change orders revise the prime contract value. source
- ERP Integrations — Prime contract change orders export (Procore→Vista; Procore→Workday as customer contract amendments). source
Receives from · 4
- RFIs — Create a potential change order from an RFI. source
- Change Events — Create a Prime PCO / Prime CO from change event lines; lines become SOV. source
- Workflows — Approval workflow on prime contract change orders / PCOs. source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
Commitment Change Orders
Change orders on subcontracts/POs.
Sends to / links with · 3
- Commitments — Approved CCOs revise the commitment; ERP-integrated companies send approved CCOs to accounting. source
- Invoicing — Only approved CCOs appear on the subcontractor invoice to bill. source
- ERP Integrations — Commitment change orders export (Procore→Vista; Procore→Workday as supplier contract amendments). source
Receives from · 4
- Change Events — Create (or bulk-create) commitment change orders from change event lines; lines become CCO SOV. source
- Workflows — Approval workflow on commitment change orders / commitment PCOs (single, two or three tier). source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
- RFQs — Once a sub's RFQ quote is reviewed and set to 'Pending Final Approval', a commitment change order created from those change event lines fills its schedule of values with the quoted amounts. source
Contracts & Cost
Prime Contracts
Owner contract and SOV; owner invoices originate here.
Sends to / links with · 4
- Budget — In Procore's standard budget view, approved prime contract change orders feed Approved COs and the Revised Budget. source
- Invoicing — Owner invoices originate from an approved prime contract. source
- ERP Integrations — Prime contracts sync (Vista→Procore; Workday customer contracts →Procore). source
- Transmittals — Add a prime contract line item or potential change order as a transmittal item. source
Receives from · 5
- Prime Change Orders — Approved change orders revise the prime contract value. source
- Estimating — Create a prime contract from an estimate. source
- Workflows — Approval workflow on Prime (Head) Contract items. source
- Locations — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
Commitments
Subcontracts and POs with SOV/SSOV; Compliance tab.
Sends to / links with · 10
- Invoicing — Subcontractor invoices are built from the commitment's Subcontractor SOV detail lines. source
- Budget — Commitment values roll into committed costs. source
- ERP Integrations — Commitments sync to the ERP (Vista: Procore→Vista; Workday: supplier contracts Procore→Workday). source
- Daily Log — Unit/Quantity-based subcontracts and POs appear in the Daily Log Productivity section. source
- Change Events — Field-initiated change orders submitted by collaborators can auto-create change events (Beta). source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Procore Pay — Procore Pay's "Insurance Compliant" payment requirement checks the commitment's status before releasing payment. source
- Transmittals — Add a subcontract or purchase order as a transmittal item. source
- Materials — Approved purchase orders and commitment change orders with described, unit-of-measure SOV lines appear in Materials as orders to receive. source
- Conversations — Send a message about a commitment; the thread appears on the item and in Conversations. source
Receives from · 9
- Bid Management — Award a bid and convert it to a subcontract or purchase order. source
- Change Events — Create a subcontract or PO from change event lines, or add lines to an unapproved commitment's SOV. source
- Commitment Change Orders — Approved CCOs revise the commitment; ERP-integrated companies send approved CCOs to accounting. source
- Estimating — Create a purchase order from an estimate. source
- Workflows — Approval workflow on Subcontract and Purchase Order items. source
- Locations — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Insurance (Directory) — Commitment Compliance tab shows Directory insurance entries and an automatic Compliant / Not Compliant status. source
- Bid Board — Create a purchase order in Commitments from a Bid Board estimate (after the estimate is sent to budget). source
Budget
Budget, budget changes, committed/actual costs, forecasts, Labor Productivity Cost view.
Sends to / links with · 6
- ERP Integrations — Budgets sync with the ERP (Vista: both ways; budget modifications and forecasts Procore→Vista). source
- Field Productivity — Importing a unit-quantity budget sets up the Field Production Report. source
- Timesheets (Project) — Budgeted hours/quantities populate the pickers in Timesheets and My Time. source
- Change Events — Creating a budget change automatically creates a linked change event. source
- Conversations — Send a message about a budget item; the thread appears on the item and in the Conversations tool. source
- Project Status Snapshots — Snapshots created from the Budget or Forecasting view are stored and surfaced in the company-level Project Status Snapshots tool. source
Receives from · 12
- Estimating — Send to Budget copies the primary estimate's line items into the project Budget; its cost codes and amounts become the budget lines (Project Financials required). source
- Timesheets (Project) — Timecard entry hours and installed quantities from Timesheets show in the Budget's Labor Productivity Cost view against budgeted hours and quantities (Resource Tracking customers). source
- Change Events — Create budget changes (adjustment + lines, amount or unit/qty) from change event lines; production quantities carry to the budget. source
- Prime Contracts — In Procore's standard budget view, approved prime contract change orders feed Approved COs and the Revised Budget. source
- Commitments — Commitment values roll into committed costs. source
- Direct Costs — Direct costs show in the budget's Direct Costs column and count toward Job to Date Costs. source
- Equipment — "See time entered for equipment in your budget." source
- Field Productivity — Approved production quantities appear in the Labor Productivity Cost budget view. source
- Workflows — Approval workflow on Budget Change items. source
- Bid Board — A Bid Board estimate reaches the Budget only after the project is added to Portfolio; Send to Budget is then run from the project's Estimating tool. source
- Project Status Snapshots — A snapshot's status can be set from the company Project Status Snapshots tool or from the project Budget tool. source
- Daily Log — Hours and installed quantities on Daily Log timecard entries show in the Budget's Labor Productivity Cost view (Resource Tracking customers; a 'Timesheet Hours' column can be added to other budget views). source
Direct Costs
Non-commitment costs (invoices, expenses, payroll) incl. imports from ERP.
Sends to / links with · 2
- Budget — Direct costs show in the budget's Direct Costs column and count toward Job to Date Costs. source
- ERP Integrations — Direct costs import from the ERP (Vista job costs/PR cost; Workday supplier invoices, journals, expense reports). source
Receives from · 0
- Nothing purpose-built.
Invoicing GAowner invoices page still titled "Beta"
Subcontractor invoices (against commitments) and owner invoices (against prime contract).
Sends to / links with · 2
- Procore Pay — Procore Pay pays approved subcontractor invoices and generates lien waivers on them. source
- ERP Integrations — Subcontractor invoices export (Vista, Workday); owner invoices to QuickBooks Online (opt-in). source
Receives from · 6
- Commitment Change Orders — Only approved CCOs appear on the subcontractor invoice to bill. source
- Commitments — Subcontractor invoices are built from the commitment's Subcontractor SOV detail lines. source
- Prime Contracts — Owner invoices originate from an approved prime contract. source
- Workflows — Approval workflow on subcontractor invoices (progress claims) and owner invoices. source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Materials — Posting a receipt against your purchase order creates a draft invoice on that PO in the Invoicing tool: the supplier's bill to you (payable), not your billing to the GC. source
Project Status Snapshots GAGA 2025-08-11; financial periods on snapshots are still in beta. source
Company-level access to budget snapshots across all projects, with approval status for formal budget reviews.
Sends to / links with · 1
Resource Management
Timesheets (Project)
Crew time, cost codes and production quantities. The project half of Procore's Resource Tracking product, alongside Crews, T&M Tickets, Timecard and My Time.
Sends to / links with · 5
- Daily Log — Timesheet entries auto-populate the Daily Log Timecards section, and Daily Log timecards auto-populate project Timesheets. source
- Budget — Timecard entry hours and installed quantities from Timesheets show in the Budget's Labor Productivity Cost view against budgeted hours and quantities (Resource Tracking customers). source
- Timesheets (Company) — Project Timesheets entries auto-populate Company Timecard and Company Timesheets; My Time entries flow to all. source
- Field Productivity — Installed units and hours recorded during Timesheets time entry feed the Field Production Report. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
Receives from · 7
- Equipment — Track equipment time in Timesheets (equipment timesheets need not be linked to a person). source
- Resource Planning — Synced people can be assigned and appear in the Crews and Timesheets tools. source
- Budget — Budgeted hours/quantities populate the pickers in Timesheets and My Time. source
- Locations — Items in these tools carry a multi-tiered location from the project Admin Locations Manager. source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Crews — Add a crew to a timesheet so timecard entries can be created for its members. source
- Directory — Timesheets draw people from the Directory: only people in the Directory who are marked as employees of your company can be added to a timesheet. source
Timesheets (Company) GACompany Timesheets timecard creation and Kiosk: Beta
Company-level review and approval of time across projects; Company Timecard; My Time mobile; Kiosk.
Sends to / links with · 4
- Timesheets (Project) — Project Timesheets entries auto-populate Company Timecard and Company Timesheets; My Time entries flow to all. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- ERP Integrations — Export Timesheets data from Procore for import into Sage 300 CRE payroll (file export; Sage 300 CRE only). source
- Webhooks / REST API — A payroll integration can read timecard data through the REST API. On the Timesheets reference page: 'List all Timesheets' (GET /rest/v1.0/projects/{project_id}/timesheets) returns all timesheets for a project, and 'List Timecard Data' (GET /rest/v1.0/companies/{company_id}/timesheets, in the page's endpoint list) returns timecard data for all employees on all projects for the current work week or a date range you set. source
Receives from · 2
- Daily Log — Daily Log Timecards carry over to the company Timecard and Company Timesheets tools. source
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
Resource Planning
People list, assignments, requests; two-way people sync with Directory; feeds Crews/Timesheets.
Sends to / links with · 3
- Directory — Two-way sync of first/last name, employee ID, mobile, email, status; job title RP→Directory only. source
- Timesheets (Project) — Synced people can be assigned and appear in the Crews and Timesheets tools. source
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
Field Productivity GArequires Resource Management + Project Financials for cost view
Unit-quantity budget, installed quantities from Timesheets, Field Production Report, Labor Productivity Cost budget view.
Sends to / links with · 1
Receives from · 3
- Timesheets (Project) — Installed units and hours recorded during Timesheets time entry feed the Field Production Report. source
- Budget — Importing a unit-quantity budget sets up the Field Production Report. source
- Change Events — Approved change-order hours and quantities update the Field Production Report. source
Resource Forecast BetaOpen beta via Procore Explore, available 2026-10-13 (successor to the Totals dashboard) source
Resource Forecast, "rebuilt from the ground up" as the successor to the Totals dashboard, adds an interactive capacity chart above the data table, flags over-capacity periods in red, tracks equipment alongside labor, and switches among six units (people, hours, days, FTE, cost, utilization); open beta via Procore Explore, available October 13, 2026
Sends to / links with · 0
- Nothing purpose-built.
Receives from · 0
- Nothing purpose-built.
Materials GAGA 2026-06-30 per Procore's what's-new post; some support process guides still carry older beta wording. source
Materials management on the platform: receive and manage inventory, issue and track materials as they move or are installed. Two process flows exist, with and without Procore Financials.
Sends to / links with · 1
Receives from · 2
- Commitments — Approved purchase orders and commitment change orders with described, unit-of-measure SOV lines appear in Materials as orders to receive. source
- Locations — Project storage locations are used as storage, to and from locations on receipts, transfers and issues. source
Crews
Groups of workers on a jobsite, each led by a Crew Lead or Foreman, used to build timesheets faster.
Sends to / links with · 2
- Timesheets (Project) — Add a crew to a timesheet so timecard entries can be created for its members. source
- Directory — Adding a worker in Crews also creates the worker as a contact in the Project and Company Directory; edits sync either way. source
Receives from · 0
- Nothing purpose-built.
Company & Platform
Permissions / Admin
Company and project Admin tools: permission templates, fieldsets, locations, webhooks.
Sends to / links with · 3
- 360 Reporting — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- ERP Integrations — Cost codes and cost types sync (Vista: both; Workday: Procore→Workday as project tasks) via company Admin/WBS. source
- Connection Manager — Company Admin sets automatic or manual approval for incoming connection requests. source
Receives from · 1
- Custom Fields — Company Admin custom fields/fieldsets apply to these 24 tools. source
Custom Fields
Company Admin custom fields and configurable fieldsets applied to 24 tools.
Sends to / links with · 25
- Permissions / Admin — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Action Plans — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Change Events — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Commitment Change Orders — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Prime Change Orders — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Commitments — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Coordination Issues — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Correspondence — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Daily Log — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Document Management — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Documents — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Drawings — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Equipment — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Incidents — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Inspections — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Invoicing — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Timesheets (Company) — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Observations — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Prime Contracts — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Punch List — Company Admin custom fields/fieldsets apply to these 24 tools. source
- RFIs — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Specifications — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Submittals — Company Admin custom fields/fieldsets apply to these 24 tools. source
- T&M Tickets — Company Admin custom fields/fieldsets apply to these 24 tools. source
- Timesheets (Project) — Company Admin custom fields/fieldsets apply to these 24 tools. source
Receives from · 0
- Nothing purpose-built.
Workflows GAlegacy workflows deprecated per procore.com/whats-new
Self-serve approval workflows for financial, correspondence, Document Management and Payments items.
Sends to / links with · 9
- Budget — Approval workflow on Budget Change items. source
- Commitments — Approval workflow on Subcontract and Purchase Order items. source
- Commitment Change Orders — Approval workflow on commitment change orders / commitment PCOs (single, two or three tier). source
- Prime Contracts — Approval workflow on Prime (Head) Contract items. source
- Prime Change Orders — Approval workflow on prime contract change orders / PCOs. source
- Invoicing — Approval workflow on subcontractor invoices (progress claims) and owner invoices. source
- Correspondence — Approval workflow on Correspondence/Custom Tool types. source
- Document Management — Approval workflow on Document Management documents (select regions). source
- Procore Pay — Payment workflow item in the company Payments tool. source
Receives from · 0
- Nothing purpose-built.
360 Reporting
Custom and single-tool reports across tools and projects.
Sends to / links with · 0
- Nothing purpose-built.
Receives from · 28
- Action Plans — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Permissions / Admin — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Change Events — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Commitments — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Coordination Issues — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Correspondence — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Daily Log — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Directory — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Documents — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Document Management — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Drawings — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Forms — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Incidents — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Inspections — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Meetings — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Observations — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Photos — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Punch List — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- RFIs — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Resource Planning — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Schedule — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Specifications — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Submittals — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Tasks — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Timesheets (Company) — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Timesheets (Project) — 360 Reporting builds reports from Action Plans, Admin, Change Events, Commitments, Coordination Issues, Correspondence, Daily Log, Directory, Documents, Document Management, Drawings, Forms, Incidents, Inspections, Instructions, Meetings, Observations, Photos, Punch List, RFIs, Resource Planning, Schedule, Specifications, Submittals, Tasks, Timecards, Timesheets (+ financial data). source
- Connection Manager — Downstream projects build 360 Reports from External RFI and External RFI Response data sets. source
- Assets — Asset data is available in 360 Reporting at company and project level. source
Analytics 2.0
Hourly-refreshed data model delivered to Power BI (reports, template, custom connector) via Databricks-based platform; Cloud Connector; bulk extract.
Features
- Analytics data. Analytics 2.0 brings your company's Procore data together for reporting: Power BI reports on trends within and across your projects, and the data itself shared to your own reporting tools or data warehouse through the Cloud Connector. source Cloud Connector Procore product page
Webhooks / REST API
Developer REST API resources and create/update/delete webhooks at company and project level.
Features
- Webhooks. Company and project admins can let third-party developers and integrators subscribe to event notifications for Procore API resources when Create, Update, or Delete actions occur. Hooks are set at company or project scope, and the resources available to subscribe to are returned by the API itself ('List Webhooks Resources', GET /rest/v1.0/webhooks/resources). source Webhook Resources API Hooks API
Sends to / links with · 0
- Nothing purpose-built.
Receives from · 1
- Timesheets (Company) — A payroll integration can read timecard data through the REST API. On the Timesheets reference page: 'List all Timesheets' (GET /rest/v1.0/projects/{project_id}/timesheets) returns all timesheets for a project, and 'List Timecard Data' (GET /rest/v1.0/companies/{company_id}/timesheets, in the page's endpoint list) returns timecard data for all employees on all projects for the current work week or a date range you set. source
App Marketplace GAAgentic apps: closed beta source
The Procore App Marketplace offers "500+ partner integrations" that Company Admins install and apply to projects; apps combine Embedded (Full Screen in the Apps menu, 400-pixel Side Panel on chosen views), Data Connector (user-level OAuth plus optional DMSA), and Agentic (closed beta) capabilities, with Marketplace apps certified by Procore and private custom apps installed by Installation Key
Sends to / links with · 0
- Nothing purpose-built.
Receives from · 0
- Nothing purpose-built.
Procore AI GAProcore AI Go, a voice-first mobile app that answers questions from project data, entered public beta at Groundbreak 2026 (2026-10-21). source
Procore AI is "construction-tailored AI that works alongside your team in Procore" — a side panel for questions over project data plus 20 pre-built agents (Digital Coworker Starter Pack, Pro, Enterprise with Agent Studio) that stage every proposed action for human approval, follow existing Procore permissions, and are metered in Procore Credits
Sends to / links with · 0
- Nothing purpose-built.
Receives from · 0
- Nothing purpose-built.
Conversations GAGA per procore.com (2024-04-17); several support sub-pages still carry "(Beta)" labels. source
Messaging across projects in web and mobile: direct and group conversations, plus two item features: Item Conversations (a thread on the item itself) and Link Project Items (link an item into any message).
Features
- Item Conversations. Message threads attached to a specific item. The thread shows on the item and in the Conversations tool. Supported in 7 tools: Budget, Change Events, Commitments, Observations, Punch List, RFIs, Submittals. source
- Link Project Items. Link items from the project into any message. 14 tools: Change Events, Commitments, Coordination Issues, Documents, Drawings, Forms, Incidents, Meetings, Observations, Punch List, RFIs, Submittals, Tasks, Transmittals. source legacy source (tool list)
- Summarize a conversation. Summarize a conversation with the built-in Summarize button, over a time range you pick. source
Sends to / links with · 7
- Budget — Send a message about a budget item; the thread appears on the item and in the Conversations tool. source
- Change Events — Send a message about a change event; the thread appears on the item and in Conversations. source
- Commitments — Send a message about a commitment; the thread appears on the item and in Conversations. source
- Observations — Send a message about an observation; the thread appears on the item and in Conversations. source
- Punch List — Send a message about a punch item; the thread appears on the item and in Conversations (not yet on iOS). source
- RFIs — Send a message about an RFI; the thread appears on the item and in Conversations. source
- Submittals — Send a message about a submittal; the thread appears on the item and in Conversations. source
Receives from · 9
- Transmittals — Link a transmittal as a project item inside a Conversations message. legacy source
- Drawings — Link a drawing or attach drawing files to a message. source
- Documents — Link a document or attach files from Documents to a message. source
- Forms — Link a form or attach form files to a message. source
- Coordination Issues — Link a coordination issue in a message. legacy source
- Incidents — Link an incident in a message. legacy source
- Meetings — Link a meeting in a message. legacy source
- Tasks — Link a task in a message. legacy source
- Directory — Group conversations import and stay in sync with the project Directory; distribution groups are selectable as recipients. source
Connection Manager GAPer tool: Drawings GA 2024-10-22; RFIs GA 2026-01-20; Submittals open beta since 2026-04-21. source
Procore Connect: connects a project to another Procore project (same or different company) so Drawings, RFIs and Submittals sync one way from the upstream project to the downstream one.
Sends to / links with · 1
- 360 Reporting — Downstream projects build 360 Reports from External RFI and External RFI Response data sets. source
Receives from · 4
- Drawings — Published drawings and drawing areas sync from an upstream project to a downstream project and stay in sync; markups and custom fields are excluded. source
- RFIs — Closed, non-private RFIs copy read-only to the downstream project's External RFIs tab, where they can be linked to internal RFIs. source
- Submittals — Distributed submittals copy read-only to the downstream project's External Items tab (open beta). source
- Permissions / Admin — Company Admin sets automatic or manual approval for incoming connection requests. source
Payment & Accounting
ERP Integrations GAMicrosoft Dynamics not among the 14
Company-level sync with 14 listed ERPs; object/direction per connector.
Sends to / links with · 6
- Budget — Budgets sync with the ERP (Vista: both ways; budget modifications and forecasts Procore→Vista). source
- Portfolio — "Send to ERP" during project creation; projects/jobs sync both ways (Vista, Workday). source
- Directory — Vendors sync (Vista: both; Workday: Workday→Procore). source
- Permissions / Admin — Cost codes and cost types sync (Vista: both; Workday: Procore→Workday as project tasks) via company Admin/WBS. source
- Procore Pay — Payment amount/date/check number sync both ways for Sage Intacct, QBO/QBD, Vista, Acumatica, Yardi, CMiC, NetSuite; one-way flags for Sage 300 CRE and Workday. source
- Cost Catalog — ERP cost codes can be added to the Cost Catalog for ERP-integrated companies and applied across Estimating and Bid Board; they carry to the budget when an estimate is sent. source
Receives from · 7
- Commitments — Commitments sync to the ERP (Vista: Procore→Vista; Workday: supplier contracts Procore→Workday). source
- Prime Contracts — Prime contracts sync (Vista→Procore; Workday customer contracts →Procore). source
- Invoicing — Subcontractor invoices export (Vista, Workday); owner invoices to QuickBooks Online (opt-in). source
- Direct Costs — Direct costs import from the ERP (Vista job costs/PR cost; Workday supplier invoices, journals, expense reports). source
- Commitment Change Orders — Commitment change orders export (Procore→Vista; Procore→Workday as supplier contract amendments). source
- Prime Change Orders — Prime contract change orders export (Procore→Vista; Procore→Workday as customer contract amendments). source
- Timesheets (Company) — Export Timesheets data from Procore for import into Sage 300 CRE payroll (file export; Sage 300 CRE only). source
Procore Pay GAUS GCs/owner-builders
Pays approved subcontractor invoices; Levelset lien waivers; insurance-compliance gate.
Sends to / links with · 1
- ERP Integrations — Payment amount/date/check number sync both ways for Sage Intacct, QBO/QBD, Vista, Acumatica, Yardi, CMiC, NetSuite; one-way flags for Sage 300 CRE and Workday. source
Receives from · 3
- Invoicing — Procore Pay pays approved subcontractor invoices and generates lien waivers on them. source
- Workflows — Payment workflow item in the company Payments tool. source
- Commitments — Procore Pay's "Insurance Compliant" payment requirement checks the commitment's status before releasing payment. source
Where data leaves Procore
The financial chain ends in the ERP. Time ends in payroll. Everything else can leave through Analytics, webhooks, the REST API, or a Marketplace app. These are the documented exits, with the generic category named rather than any one company’s stack.
per the cited page: jobs/vendors/cost codes/budgets both; budget mods, forecasts, commitments, CCOs, PCCOs, sub invoices Procore→ERP; prime contract, job costs, direct costs ERP→Procore; payments both source
Timecard data can be read through the REST API. The Timesheets reference lists 'List all Timesheets' (GET /rest/v1.0/projects/{project_id}/timesheets, one project) and 'List Timecard Data' (GET /rest/v1.0/companies/{company_id}/timesheets, all employees on all projects); the Timecard Entries reference adds 'List timecard entries (Company)'. Procore documents a Timesheets file export for Sage 300 CRE. Resource Planning takes a people and project sync from your system of record through Quick Connect, API, or SFTP. source Timecard Entries API Sage 300 CRE export Resource Planning integrations
Analytics 2.0 Power BI reports, template and custom connector; Databricks-based; Cloud Connector; bulk extract; hourly refresh. Fabric is not named on the fetched pages. source
Company/project webhooks POST JSON on create/update/delete; 28-day event history; retries then discard after 12 h source
Marketplace apps and iPaaS connectors move projects, users, companies, RFIs, submittals, files and timecard entries in and out of Procore; the specific objects depend on the app. source
Link files from a connected SharePoint site into Document Management Uploads (not available to US accounts per page) source
Project-level asset register exports asset properties, linked records, attachments and edit history for facilities and maintenance systems; Procore and IBM announced a collaboration (2026-10-21) to carry asset data into IBM Maximo. COBie export is not yet available. source
Procore AI agents, by tool
Twenty named agents read from and write to specific tools. The mapping below is from Procore’s public agent pages. Packaging and pricing are deliberately left out — check procore.com/ai for current terms.
Checks bids against project scopes, drawings, and specs to find gaps and exclusions.
Places subcontractor bids side by side in one matrix, highlighting missing scope and price differences.
Reviews changes, RFIs, drawings, and records for scope shifts, cost exposure, and schedule risk.
Compares contracts and drawings against internal benchmarks and flags conflicts.
Turn jobsite photos, emails, video, and voice memos into complete daily logs"; "drafts your daily logs for final human verification".
Answers questions across specs, drawings, RFIs, and submittals, with citations.
Scans drawings for coordination issues, missing details, and constructability risks.
Cross-checks drawings against specs to catch conflicts and gaps.
Quick, structured answers to everyday questions from connected Procore data.
Map photos, videos, and voice notes into categorized Procore Observations automatically"; drafts observations for review.
Track budget line items, commitments, and change events to stay ahead of potential cost overruns"; executive summary of cost trends.
Finds trends in RFIs, changes, and logs and turns them into reusable lessons and preventive actions.
Turns "raw meeting recordings and notes" into structured notes with assigned action items; separates internal vs customer tasks.
Reviews site photos for visible progress, installed work, and quality or safety concerns.
Extracts long-lead items, submittal requirements, and delivery dates from project files"; links submittal approvals to milestone dates; outputs an "exportable" structured log.
Analyzes project drawings and historical data to draft complete, pre-populated RFIs for your review.
Reviews milestones, logic, and activity relationships to flag sequencing issues and delays.
Scans documents, drawings, and specs to extract tasks, deliverables, and requirements.
Identifies hazards from site photos, videos, and drawings and produces field-ready findings.
Cross-checks submittals against specs and contracts to flag compliance gaps.
How to read the gaps
The map only draws a handoff when Procore’s public documentation describes it. A few handoffs people commonly assume — a meeting item becoming an RFI, an inspection item going straight to a punch item — aren’t described there as of the map date, so they aren’t drawn. Some are real gaps. Some may be documented somewhere the public search didn’t reach. If you can point to the page, send it and the map gets updated.
Document well. Stay safe. Get home to your family.